Snowmass
Hot Topic #3
Chamber
Science and Technology
Reliability,
maintainability and availability of fusion energy systems
Core
Working Group Opinion Paper
Core
Working Group
Mark
Tillack, Brad Nelson
Lee
Cadwallader, Dave Petti, Ron Miller, Wayne Reiersen, Phil Heotzenroeder
Les
Waganer, Tom Shannon, Mahmoud Youssef
Subtopics:
1. What
are the requirements for reliability, maintainability, and inspectability?
What values of failure rate, repair time, and component lifetime are needed to
meet reasonable availability goals?
2. How
can we quantify fusion component reliability and maintenance time?
3. How
do other technologies achieve reliability and maintainability?
4. How
can the fusion program achieve designs with high availability?
Report
Outline:
1.
Introduction (Tillack/Nelson)
2.
Subtopic 1 (
Miller)
each
subtopic to have this structure:
a.
problem statement
b.
discussion (community views)
c.
recommendations (consensus if possible)
3.
Subtopic 2 (
Reiersen/Heitzenroeder)
4.
Subtopic 3 (
Cadwallader)
5.
Subtopic 4 (
Nelson)
Introduction
Availability
is a primary metric for an attractive power plant, directly affecting the cost
of electricity. Beyond the COE, power plant operators will be averse to the
uncertainties associated with unplanned outages. Regulators also may take a
dim view of frequent failures in a system containing large inventories of
radioactive materials.
Fusion
system designs to date have incorporated availability projections in a
relatively primitive way, without distinguishing between the unique attributes
of various design concepts. Many factors contribute to the plant availability,
including both planned and unplanned outages, failure rates of different power
core technologies, component lifetime, and the time to perform regular
maintenance or to diagnose and recover from failures with different levels of
severity.
This
hot topic will be discussed in four major subtopics which will help to
characterize the nature of the problem and seek solutions. The subtopics are
further discussed below.
Subtopic
1
What
are the requirements for reliability, maintainability, and inspectability?
What values of failure rate, repair time, and component lifetime are needed to
meet reasonable availability goals?
Availability
is governed by both planned and unplanned outages. The simplest formula that
accounts for both planned (f
p)
and forced (f
f)
outage rates is:
A
= (1 – f
p)
(1 – f
f)
where
the forced outage rate is governed by the mean time between failures (MTBF) and
the mean time to repair (MTTR):
(1
– f
f)
= MTBF/(MTBF+MTTR)
Fission
plants typically are projected to operate at plant capacity factors near 80%,
which sets an important goal for fusion. The allocation of component lifetime,
failure rate, and maintenance time is important in order to establish goals for
fusion development and to allow evaluation and comparison between different
confinement concepts and power plant technologies. In the establishment of
quantitative and quantifiable goals for availability, consideration must be
given to a variety of concerns. For example, the time to recover from a
failure will depend on the severity and consequences of the failure as well as
the inherent maintainability or redundancy of the configuration.
This
sub-topic will provide for discussion of the various complexities of
availability allocation and attempt to offer guidance for design and R&D
programs in establishing the ability of concepts to meet acceptable
availability goals.
Subtopic
2
How
can we quantify fusion component reliability and maintenance time?
Without
test data, can we project reliability from other technologies?
Quantifying
reliability and maintainability for a technology still in its early stages of
development is difficult. Substantial testing is needed to obtain confidence
in reliability projections. In the absence of testing in a prototypical
environment, estimates of availability have been made by deconstructing
conceptual designs into sub-elements that resemble sub-elements from related
technologies, such as the fission or aerospace industries. The resulting
availability can be quite low, and the accuracy of these estimates is
questionable, but the process can help identify problem areas in the design.
Design improvement is an essential step in the quest for high reliability.
Maintenance
times have been studied for some power plant designs using detailed time-line
projections. Similar to reliability estimates, the sequence of operations to
remove power core components can be deconstructed into individual linear
motions, and connect/disconnects of coolant, electrical, vacuum, and other
systems. The accuracy of these estimates also entails substantial
uncertainties, and is also highly design-dependent.
This
sub-topic will provide for discussion of the various methodologies for
estimating failure rates and maintenance times and the uncertainties in those
methodologies. Application of these methods to various confinement concepts
and power core technologies will be used to highlight the potential differences
between design concepts.
Subtopic
3
How
do other technologies achieve reliability and maintainability?
The
primary mechanisms for achieving reliability and maintainability in other
technologies are: 1) testing of components and systems, 2) standardization, 3)
careful attention to maintenance to avoid unplanned downtime (including in-situ
inspection), and 4) a slow evolution of design and technology based on
accumulated experience. In addition, redundancy and failure tolerance are
important factors.
The
aircraft industry, for example, has developed passenger planes that are
extremely reliable with very little downtime for unplanned maintenance. After
initially pursuing widely different means for passenger air travel, the
industry settled on multiple-engine airplanes (redundancy) with aluminum
structure. The dirigible was superior to the early airplanes in almost every
respect, but was finally rejected because of a single reliability problem. The
industry has since standardized on many items (a few engine designs with
predictable reliability) and any new aircraft requires extensive testing of
every system as well as flight tests of prototypes.
The
fission industry has not standardized on a design in the US, but has relied on
a strong maintenance program to show a continued increase in availability, even
though many plants are nearing the end of their life. In contrast, the new
plants being built overseas are almost all based on standard designs. In
addition, almost all components are built according to strict design safety
codes (e.g. ASME Section III), which are themselves the product of extensive
testing and experience.
This
subtopic will provide for discussion of the availability of other complex
technologies, and how these technologies have improved their availability over
time. Anlalogies will be sought between these technologies and various
components of a fusion reactor.
Subtopic
4:
How
can the fusion program achieve designs with high availability?
The
availability of a fusion reactor is perceived to be poor, due to the complexity
of present design concepts, the difficulty of repair, and the harsh operating
environment of the internal components. These are only perceptions, however,
and cannot be based on experience, since there are no operating fusion
reactors. The first step for the fusion program to achieve reliable and
maintainable systems is to include these attributes as top level requirements
for a power plant, on a par with initial capital cost and efficiency.
Once
reliability and maintainability are recognized as a top level goals, the design
of the power plant probably will be steered in obvious directions, including
more modular designs with standardized components that operate with significant
margin and, where possible, redundancy. The designs will be tolerant of a few
minor failures before maintenance is required. The maintenance procedures
themselves will be simplified to take advantage of the modular approach.
Finally, the power plant concepts themselves may have to be judged based on
features that are inherently more reliable or maintainable. A steady state
concept may be selected over a pulsed concept, or a concept that does not
disrupt may be favored over one that must deal with plasma disruptions.
This
subtopic will provide for discussion of the key elements involved in improving
fusion reactor availability. Included will be an attempt to identify features
of present concepts that are thought to require attention, and what testing and
test facilities may be needed to validate the designs of the components.
Session
Plan:
(from
Prospectus)
Prior
to the summer study
,
three activities will be carried out:
1. A
survey will be prepared and disseminated to the full Snowmass participant list.
This survey will determine the opinions of the community on this subject and
attempt to stimulate interest in the session (through provocative wording of
the questions). For example, participants will be asked to rank different
confinement concepts and technologies. Responses will be collected and
prepared for distribution at the meeting.
2. Discussion
leaders (coauthors) will prepare a set of discussion points for each sub-topic.
Backup material will be prepared for each discussion point (to be used only if
needed).
3. A
detailed outline of the report will be prepared by the authors. This draft
should include a statement of the problem, but should not render conclusions or
prejudge the outcome of the meeting.
During
the summer study
,
two discussion periods are anticipated for each subtopic.
1. A
brief opening speech will be given (on Monday or Tuesday) by the session
chairmen in order to explain the topic and discuss the survey responses.
2. During
the first week, each subtopic will be allocated a separate period of discussion
led by the discussion leaders/authors (see below). The discussion leaders will
be allowed a 5-10 minute opening statement to guide the discussion, followed by
~1 hour of moderated discussion. One subtopic will be discussed each day
(Tuesday–Friday).
3. After
the discussion periods, discussion leaders will prepare a presentation that
articulates the main points of view. Involvement should be sought from the
community in drafting preliminary reports. In addition, a 1-page viewgraph
will be prepared for a summary report presentation on July 19.
4. During
the second week, discussion leaders will present their preliminary findings and
offer opportunities for further community discussion.
Following
the summer study
,
the final report will be prepared. The chairmen will collect contributions
from the authors and serve as editors.